The process of making an overhead bridge in kwara state.

in GEMS2 years ago

Evening everyone, its another new working week and I hope everyone have a good day. Its been a while posting on community because I was so busy with work at my place of work and as well observing the progress of the overhead bridge which is going on in my state, which is kwara state.

FB_IMG_16633428941974764.jpg
As promise, the administration of Mallam Abdulrahman Abdulrazaq which is the governor of the state. Still on track towards the completion of the General Babatunde Idiagbon flyover bridge.
We have doubled up our effort on schedule. Work is going as planned and the scheduled date for completion remain December 2022.
Below is the breakdown of construction activities since the commencement of the project

FB_IMG_16633429213810331.jpg

FB_IMG_16633428993763826.jpg

  • completed activities
  • pile 100 percent
  • pile caps 100 percent completed
  • piers 100 percent completed
  • precast beams 100 percent completed
  • concrete casing protection for NNPC pipeline 100 percent completed
  • ongoing activities for the week
  • final reinforcement for abutment wall 1
  • second phase of concreting for abutment wall 2
  • concreting of capping beam 1
  • concreting of capping 2
  • formwork and concreting of retaining wall stem (60percent)
  • line drainage
  • concreting of retaining wall base
  • concreting of precast parapets

FB_IMG_16633428819706111.jpg

FB_IMG_16633429023094625.jpg
And with all this pictures that was show, the work is still going on.
FB_IMG_16633429049625165.jpg

FB_IMG_16633428993763826.jpg

FB_IMG_16633429154138688.jpg

FB_IMG_16633429213810331.jpg

FB_IMG_16633429245716760.jpg

FB_IMG_16633429023094625.jpg

FB_IMG_16633428968824919.jpg