20210820 Bungalow construction (concrete columns) - day 45

in Pentarchitecture4 years ago (edited)

The white line that frames the bedroom is a 3cm x 3cm metal square tubing that will help create the 3cm step to stop rain water from going inside. It will be removed once the concrete is cured.
20210820.1.jpeg
20210820.5.jpeg
IMG_8036.jpg

Metal base plates for the columns at each angle.
IMG_8038.jpg
IMG_8039.jpg
IMG_8040.jpg

The concrete columns that will support the outer part of the floating slab which will become the floor of the living room are complete.
20210820.2.jpeg
IMG_8025.jpg

Metal to reinforce the beams of that concrete slab.
20210820.3.jpeg
20210820.6.jpeg

The steps of the outside corridor that will lead to the entrance of the workshop are taking shape.
20210820.4.jpeg

Sort:  

Congratulations @igb! You have completed the following achievement on the Hive blockchain and have been rewarded with new badge(s) :

You distributed more than 10 upvotes.
Your next target is to reach 50 upvotes.
You published more than 40 posts.
Your next target is to reach 50 posts.

You can view your badges on your board and compare yourself to others in the Ranking
If you no longer want to receive notifications, reply to this comment with the word STOP

To support your work, I also upvoted your post!