Cleaning up the broken pile head slag
After the pile head is chiseled to the design elevation position, the pile surface will be leveled...
The remaining work is to clean the slag. If the location conditions are met, it will be cleaned with a machine. If conditions do not permit, it can only be cleaned manually.
The reinforcement team has to adjust the core reinforcement of the pile, and the reinforcement of each pile has to be adjusted to check whether the anchorage length meets the specification.
If it is too long, it must be cut off, otherwise the platform will be exposed, which is not easy to handle. Prepare to do the next step to accept the pile core, which requires small and large stools. These two items need to be checked by a third party. When all materials are ready, report to a third party for testing!
It's so troublesome. Fortunately, it hasn't rained these days. If it rains, the difficulty will be greatly increased.