It is difficult to say a few months ago my team and I worked on the stone foundation. All so perfect our work can be said to be good 98%, we are happy
After running for almost six months, during which the rainy season arrived.
The water discharge is so heavy that it destroys the stone foundation wall of the river, the water discharge is so heavy that it erodes the soil in the area around the embankment
The water pushed to the left side and blocked the aqueduct road
Heavy rainfall does make the impossible possible.
All work becomes meaningless. Satisfactory results now seem to be useless with its function. And it must be repaired even though there is material that must be spent to repair it again.
Here are some snapshots of events, hostile nature changes everything we are proud of but the results are not comparable to what we anticipated.